Outfitting & System Installation

Back to Home Page
Gantt Chart

Gantt Chart

Gantt Chart Sample
(Sample Gantt chart for Outfitting & System Installation tasks)
Overall % Complete
0%
Total Planned Duration
0 days
Total Actual Duration
0 days
Total Baseline Duration
0 days
Baselining Controls & Info
(Baselining: captures current planned dates as project baseline for Oceanic Shipyards Pvt Ltd)
Current Baseline Status: Active Baseline Date: 2024-06-15 09:30 UTC Set By: Eric Cheng (Lead PM, Oceanic Shipyards Pvt Ltd) Company: Oceanic Shipyards Pvt Ltd Project: MV Blue Horizon - Outfitting & System Installation
Baseline History: (Select to view previous baselines)
Baseline Audit Trail:
# Date Changed By Role Change Category Reason Impact Risk Rating Stakeholder Comments Lessons Learned Approved By
3 2024-06-15 Eric Cheng Lead PM Major Scope Change Stakeholder re-approval after scope change +5 days to overall schedule High "Scope change accepted, risk mitigated" - S. Rao (Owner Rep) Early risk review required for scope changes Subash Chandran
2 2024-06-01 Subash Chandran Project Manager Delay Material delivery delay +2 days to procurement Medium "Supplier notified, contingency used" - J. Mathews Supplier contracts should include penalties Eric Cheng
1 2024-05-20 John Mathews Procurement Lead Initial Baseline Project kickoff N/A Low "Ready to start" - S. Rao Baseline set after stakeholder sign-off Subash Chandran
Baseline Change Request (Mock Form):
(Change requests require formal approval, impact analysis, risk review, and audit logging)
Stakeholder Notification Log (Mock):
Date Stakeholder Role Notification Type Comments
2024-06-15 S. Rao Owner Rep Baseline Change Scope change accepted
2024-06-01 J. Mathews Procurement Lead Delay Notification Supplier contingency used
2024-06-01 Priya Nair QA Manager Risk Alert QA checks rescheduled
2024-05-20 Eric Cheng Lead PM Baseline Set All stakeholders notified
PMP Baselining & Change Control Notes:
  • Baseline Management: The baseline is the approved reference for scope, schedule, and cost. All project performance is measured against it.
  • Change Impact Analysis: Every baseline change must include an impact analysis (schedule, cost, risk).
  • Risk Management: Baseline changes are reviewed for risk and mitigation strategies.
  • Audit Trail: All baseline changes are logged for traceability and future reference.
  • Stakeholder Communication: Baseline changes must be communicated to all relevant parties and documented.
  • Lessons Learned: Each baseline change should be reviewed for lessons learned and process improvement.
Mock Baseline Values:
System Baseline Start Baseline End Baseline Duration Lead Engineer Vendor Risk
Main Engine Installation 2024-07-01 2024-07-10 10 days Ravi Kumar MarineTech Ltd Medium
Electrical System Cabling 2024-07-11 2024-07-20 10 days Priya Nair ElectroShip Pvt Low
HVAC System Installation 2024-07-21 2024-07-28 8 days Sunil Joshi CoolMarine Inc Medium
Fire Safety System 2024-07-29 2024-08-05 8 days Meera Singh SafeShip Solutions High
Navigation System 2024-08-06 2024-08-12 7 days Arjun Patel NavStar Marine Low
Ballast Water System 2024-08-13 2024-08-18 6 days Fatima Noor EcoMarine Equip Medium
Baseline Comparison (Mock):
System Baseline End Current Planned End Deviation Deviation Type Root Cause
Main Engine Installation 2024-07-10 2024-07-12 +2 days Delay Alignment issue
Electrical System Cabling 2024-07-20 2024-07-20 0 days On Baseline -
HVAC System Installation 2024-07-28 2024-07-27 -1 day Ahead Vendor efficiency
Fire Safety System 2024-08-05 2024-08-06 +1 day Delay Inspection hold
Navigation System 2024-08-12 2024-08-12 0 days On Baseline -
Ballast Water System 2024-08-18 2024-08-17 -1 day Ahead Pre-assembly
(Summary: 2 systems delayed, 2 ahead, 2 on baseline)
Baseline Risk Register (Mock):
Risk System Likelihood Impact Mitigation Status
Vendor Delay Main Engine Installation Medium High Penalty clause, backup vendor Mitigated
Inspection Hold Fire Safety System Low Medium Early QA scheduling Open
Design Change Ballast Water System Low Low Design freeze Closed
Baseline Approval Workflow (Mock):
Baseline Approval Workflow
(Workflow: Request → PM Review → Stakeholder Approval → Baseline Set → Notification)
Baseline Change Log (Summary):
  • 3 baseline changes recorded in audit trail.
  • All changes approved by project manager and stakeholders.
  • Notifications sent to 4 key stakeholders.
  • 2 risks mitigated, 1 open risk under review.
Baseline KPI Dashboard (Mock):
  • Baseline Adherence: 67%
  • Average Deviation: +0.5 days
  • Risk Closure Rate: 66%
  • Stakeholder Satisfaction: High
Baseline Lessons Learned (Mock):
  • Early coordination with vendors reduced installation delays.
  • Change control discipline improved schedule reliability.
  • Stakeholder feedback helped optimize system sequencing.
  • Audit trail and notification logs improved transparency.
  • Risk register and mitigation planning reduced project impact.
  • Approval workflow streamlined baseline changes.
Deviation Highlight:
  • Orange border = delayed vs baseline
  • Green border = ahead of baseline
  • No border = on baseline
# System Description Planned Start Planned End Actual Start Actual End Baseline Start Baseline End Planned Duration Actual Duration Baseline Duration Status Progress Comments